Chapter 10 Rectification after completion of works
The contractor’s failure to perform work in accordance with the construction contract is a breach of contract and entitles the principal to sue the contractor for damages at common law.
However, most construction contracts include contractual mechanisms which:
- allow the contractor to return to the site to rectify defects;
- nominate a defects liability period (‘DLP’) which is a period after practical completion during which the principal or its representative (usually the superintendent) may, by notice, require the contractor to rectify defects;
- entitle the principal to have a third party rectify the defect if the contractor does not follow the rectification notice; and
- allow the principal access to security or retention to pay for the rectification.