D’Arcy v Queensland Building and Construction Commission [2026] QCA 200
Sian Keast | Elissa Morcombe | Oliver Conroy
Key takeoutÂ
Work done on an individual residential unit within a building of more than 3 storeys falls within the exclusion in section 26(a) of the Queensland Building and Construction Commission Regulation 2018 (Qld) (QBCC Regulation) and is not eligible for cover under Queensland’s Home Warranty Scheme (Scheme).
The consumer protection purpose of the Scheme does not override the plain words of the exclusion. Section 67WB(1)(f) of the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act) expressly authorises regulations to exclude types of building work from the Scheme. Where that line is drawn is a policy decision, not a matter for the courts.
Owners should not assume renovation work is covered by the Scheme simply because a premium has been paid and the Queensland Building and Construction Commission (QBCC) has issued a notice of cover.
Facts
In October 2021, D’Arcy engaged a licensed builder to renovate the bathroom and kitchen of her tenth-floor apartment in Surfers Paradise. The builder collected the Scheme premium from D’Arcy and paid it to the QBCC, which issued D’Arcy a notice of cover.
The builder started but refused to complete the work after falling into dispute with D’Arcy. D’Arcy made a claim under the Scheme for assistance with the reasonable cost of completing the work.
The QBCC refused the claim on the basis that section 26(a) of the QBCC Regulation excluded work ‘on or for’ a ‘multiple dwelling‘ of ‘more than 3 storeys‘.
D’Arcy applied to the Queensland Civil and Administrative Tribunal (QCAT) for an external review of the QBCC’s decision. Both QCAT and the QCAT Appeal Tribunal upheld the QBCC’s decision to reject D’Arcy’s claim.
D’Arcy then sought leave to appeal the decision to the Queensland Court of Appeal under section 150(3) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
Decision
The Court of Appeal dismissed the application for leave to appeal with costs.
D’Arcy raised 2 proposed grounds of appeal in support of her application for leave:
- that section 26(a) of the QBCC Regulation had been incorrectly interpreted; and
- that section 26(a) of the QBCC Regulation was invalid.
The Court of Appeal ruled that neither ground had any prospect of success and therefore refused leave to appeal the decision.
Ground 1: Statutory interpretation of section 26(a) of the QBCC Regulation
D’Arcy argued that, on its proper interpretation, the words ‘work on or for a… multiple dwelling’ in the section 26(a) exclusion did not include work done on part of a multiple dwelling, such as an individual residential unit, and should be confined to work on the building itself (for example, exterior walls or common property).
The Court rejected this submission. The Court held that the text of the legislation ‘unambiguously encompasses’ work done on a residential unit within the building. The provision does not distinguish between work on the structure of the building and work done within it, and D’Arcy’s interpretation introduced a restriction not found in the provision. This was reinforced by the definition of ‘multiple dwelling’ as ‘a building comprising 2 or more separate residential units, other than a duplex’. Since the multiple dwelling consists of residential units, work done on one of those units is work done on part of the multiple dwelling itself, and therefore ‘work on or for’ the multiple dwelling. The Court further noted that the examples given in section 26(a), which expressly refer to renovating the bathroom of a single residential unit in a 10-storey multiple dwelling, were consistent with this interpretation.
Ground 2: Validity of section 26(a) of the QBCC Regulation
D’Arcy also contended that section 26(a) of the QBCC Regulation was invalid as subordinate legislation on the basis that it was inconsistent with the QBCC Act or beyond the proper scope of the regulation-making power.
The Court rejected this submission. Section 67WB(1) of the QBCC Act lists categories of building work not eligible for assistance under the Scheme and, in section 67WB(1)(f), expressly authorises regulations that exclude other types of building work. Nor was the regulation so lacking in reasonable proportionality that it was not a real exercise of power. The Court emphasised that the three-storey threshold reflects a policy choice made by Parliament and it is not for the courts to replace that choice with their own. Section 26(a) was therefore found to be valid.
Gulf Civil Pty Ltd v K & F Group Pty Ltd [2026] QSC 221
Michael Creedon | Charlotte Gordon | Sarah Nichols
Key takeout
- A hire agreement stated to be ‘ongoing until return of machinery’ may stay on foot, and support a security of payment claim, while any single item remains deployed.
- A solicitor’s letter affirming that a hire agreement remains in place can confirm a ‘construction contract’ or itself create an ‘other arrangement’ under section 64 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act).
- A party challenging an adjudicator’s jurisdiction bears the onus of proving there was no construction contract. Gaps in evidence count against it.
Facts
On 20 March 2022, K & F Group Pty Ltd (K & F) and Gulf Civil Pty Ltd (Gulf Civil) entered into a document for the hire of plant (Hire Agreement). The Hire Agreement identified K & F as the ‘Owner’ and Gulf Civil as the ‘Hirer’. At the time, both companies were controlled by Owen Whish (Whish).
The Hire Agreement was to be read in conjunction with the ‘Agreement Particulars’. The Agreement Particulars were to be entered into on each and every occasion that K & F hired plant to Gulf Civil. However, only one set of Agreement Particulars was ever prepared (on 20 March 2022). It recorded a commencement date, described the duration as ‘ongoing until return of machinery’, and listed 22 items of plant and equipment with hourly and monthly hire rates.
The plant and equipment listed in the Agreement Particulars was subsequently deployed and used by Gulf Civil. As time went on, items were returned to K & F’s depot and redeployed from time to time.
In mid-2025, Whish entered negotiations for the sale of Gulf Civil and also offered to sell the deployed K & F equipment to Gulf Civil. On 4 August 2025, Haribol Civil Pty Ltd acquired all the shares in Gulf Civil. At meetings on 4 and 5 August, Whish told Gulf Civil’s new owner that Gulf Civil could use the deployed plant free of charge while it considered whether to buy it. Some weeks later, Gulf Civil declined to purchase the plant.
On 27 August 2025, K & F purported to terminate the Hire Agreement on 14 days’ notice. On 19 September 2025, Gulf Civil’s then solicitors responded (19 September Letter). The letter stated that the Hire Agreement set out the basis on which K & F had hired the plant to Gulf Civil, that K & F had no unilateral right to terminate it, and that it would end when the plant was returned. Gulf Civil progressively returned the plant, with all items returned by December 2025.
On 2 January 2026, K & F issued a payment claim for $1,143,388 to Gulf Civil. The payment claim was made under the BIF Act and claimed hire charges, repair costs, loss-of-use damages, servicing and compliance costs, and a demobilisation charge. Hire charges for each item ran from 4 August 2025 (the date of the share sale), and most were calculated using rates said to be drawn from the Agreement Particulars.
On 23 January 2026, Gulf Civil issued a payment schedule in response to K & F’s payment claim. The payment schedule assessed the amount payable as ‘$nil’, noting that there was no clear contractual basis for the entitlement. Gulf Civil claimed that the hire charges were not properly incurred under the Hire Agreement and that it never accepted that such charges would accrue after completion of the share sale.
On 6 March 2026, K & F applied for adjudication under the BIF Act. On 7 May 2026, the adjudicator determined K & F was entitled to $301,768.
By application to the Supreme Court of Queensland, Gulf Civil sought orders that the adjudication decision be set aside or declared void for want of jurisdiction. It contended that the adjudicator erred in determining the charges were incurred under a ‘construction contract’ within the meaning of section 64 of the BIF Act.
Decision
Gulf Civil’s application was dismissed. The Court found that Gulf Civil failed to demonstrate that the adjudication decision was made in the absence of the necessary jurisdictional fact of the existence of a construction contract.
Did the Hire Agreement constitute a ‘construction contract’?
The Court found that the Hire Agreement was a ‘rolling hire agreement’.
In reaching this decision, the Court noted that there were ‘obvious oddities and inconsistencies’ in the Hire Agreement. For instance, defined terms referred to annexures or schedules that did not exist, and text was missing from the end of the document. Despite such anomalies, the Court had ‘no doubt’ that the Hire Agreement constituted a concluded agreement whereby K & F agreed to hire plant to Gulf Civil from 20 March 2022, in return for Gulf Civil paying hire charges at the rates set out in the Agreement Particulars.
The Court noted that the Hire Agreement’s ‘character’ largely turned upon the proper construction of the ‘Entire Agreement’ clause. The Entire Agreement clause required Agreement Particulars to be entered into each time plant was hired and stated that any further Agreement Particulars would be subject to the Hire Agreement’s terms. This was suggestive of a framework agreement. However, such language was also in tension with the duration stated in the Agreement Particulars (ie ‘Ongoing until return of machinery’). When considering this, the Court noted that the real issue was not how the Hire Agreement ought to be characterised in the abstract, but rather when it would end. With that focus, the Court found that the Hire Agreement was properly characterised as a ‘rolling hire agreement’. That was apparent from reading the entire agreement, having regard to its context and the commercial purposes or objectives it sought to secure.
The Court concluded that a reasonable businessperson would have understood that the Hire Agreement was intended to provide for ‘a continuing, rolling hire agreement’. The Court construed the duration in the Agreement Particulars to mean ‘ongoing until the return of all machinery’. That interpretation was consistent with clause 37(c) of the Hire Agreement, which stated, ‘the singular includes the plural’.
The Court noted that Gulf Civil’s construction would produce an ‘unwieldy result’ and one which would ‘frustrate the commercial objects that were sought to be secured by the contract’. That is, each item would only be hired for one discrete ‘Hire Period’ and could not be remobilised without entering into a new set of Agreement Particulars. When considering the alternative construction, the Court suggested that ongoing projects requiring the use of the plant could be unnecessarily delayed until further Agreement Particulars were finalised. There would also be ‘a slew of different Agreement Particulars unnecessarily accumulating’, which could not have been the parties’ intention.
Was the Hire Agreement still on foot as of 4 August 2025?
The Court found that the Hire Agreement remained on foot as of 4 August 2025.
In reaching this decision, the Court noted that there was no evidence of when and how the 22 items listed in the Agreement Particulars were returned and redeployed. However, it seemed more likely than not that most of the items had been returned at some time. Notably, the evidence did not establish that all items had been returned at any one point in time (which would have brought the Hire Agreement to an end). In particular, a dozer listed in the Agreement Particulars had remained deployed at Gulf Civil’s Jardine River project since 2024. As a result, the Court rejected the argument that there was no ‘construction contract’ from 4 August 2025 onwards.
The Court held that the 19 September Letter confirmed the existence of the Hire Agreement as a ‘construction contract’ (with effect from at least 4 August 2025). Whish’s ‘free of charge’ statement did not change this. Whatever its effect on Gulf Civil’s liability for hire charges in the interim, it did not affect the Hire Agreement’s continued existence. In the alternative, the Court held that even if it was wrong about the proper construction of the Hire Agreement, the 19 September Letter would nonetheless amount to an ‘other arrangement’ under section 64 of the BIF Act. Once the 19 September Letter was sent, there was a concluded, bilateral state of affairs under which K & F undertook to supply (and had supplied) plant for hire to Gulf Civil. By its conduct, Gulf Civil adopted and confirmed the arrangement documented in the Hire Agreement.
The Court considered that Gulf Civil’s adoption of the Hire Agreement operated retrospectively from 4 August 2025 but held that this was ‘immaterial’. According to the Court, the 19 September Letter showed that there was an arrangement constituting a ‘construction contract’ (at least from 19 September). That was all that was required for the adjudicator to have jurisdiction to decide the application. Any errors about entitlement to particular hire charges or charging periods were errors within the adjudicator’s jurisdiction and did not invalidate the decision.
D’Arcy v Queensland Building and Construction Commission [2026] QCA 200
Sian Keast | Elissa Morcombe | Oliver Conroy
Key takeoutÂ
Work done on an individual residential unit within a building of more than 3 storeys falls within the exclusion in section 26(a) of the Queensland Building and Construction Commission Regulation 2018 (Qld) (QBCC Regulation) and is not eligible for cover under Queensland’s Home Warranty Scheme (Scheme).
The consumer protection purpose of the Scheme does not override the plain words of the exclusion. Section 67WB(1)(f) of the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act) expressly authorises regulations to exclude types of building work from the Scheme. Where that line is drawn is a policy decision, not a matter for the courts.
Owners should not assume renovation work is covered by the Scheme simply because a premium has been paid and the Queensland Building and Construction Commission (QBCC) has issued a notice of cover.
Facts
In October 2021, D’Arcy engaged a licensed builder to renovate the bathroom and kitchen of her tenth-floor apartment in Surfers Paradise. The builder collected the Scheme premium from D’Arcy and paid it to the QBCC, which issued D’Arcy a notice of cover.
The builder started but refused to complete the work after falling into dispute with D’Arcy. D’Arcy made a claim under the Scheme for assistance with the reasonable cost of completing the work.
The QBCC refused the claim on the basis that section 26(a) of the QBCC Regulation excluded work ‘on or for’ a ‘multiple dwelling‘ of ‘more than 3 storeys‘.
D’Arcy applied to the Queensland Civil and Administrative Tribunal (QCAT) for an external review of the QBCC’s decision. Both QCAT and the QCAT Appeal Tribunal upheld the QBCC’s decision to reject D’Arcy’s claim.
D’Arcy then sought leave to appeal the decision to the Queensland Court of Appeal under section 150(3) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
Decision
The Court of Appeal dismissed the application for leave to appeal with costs.
D’Arcy raised 2 proposed grounds of appeal in support of her application for leave:
- that section 26(a) of the QBCC Regulation had been incorrectly interpreted; and
- that section 26(a) of the QBCC Regulation was invalid.
The Court of Appeal ruled that neither ground had any prospect of success and therefore refused leave to appeal the decision.
Ground 1: Statutory interpretation of section 26(a) of the QBCC Regulation
D’Arcy argued that, on its proper interpretation, the words ‘work on or for a… multiple dwelling’ in the section 26(a) exclusion did not include work done on part of a multiple dwelling, such as an individual residential unit, and should be confined to work on the building itself (for example, exterior walls or common property).
The Court rejected this submission. The Court held that the text of the legislation ‘unambiguously encompasses’ work done on a residential unit within the building. The provision does not distinguish between work on the structure of the building and work done within it, and D’Arcy’s interpretation introduced a restriction not found in the provision. This was reinforced by the definition of ‘multiple dwelling’ as ‘a building comprising 2 or more separate residential units, other than a duplex’. Since the multiple dwelling consists of residential units, work done on one of those units is work done on part of the multiple dwelling itself, and therefore ‘work on or for’ the multiple dwelling. The Court further noted that the examples given in section 26(a), which expressly refer to renovating the bathroom of a single residential unit in a 10-storey multiple dwelling, were consistent with this interpretation.
Ground 2: Validity of section 26(a) of the QBCC Regulation
D’Arcy also contended that section 26(a) of the QBCC Regulation was invalid as subordinate legislation on the basis that it was inconsistent with the QBCC Act or beyond the proper scope of the regulation-making power.
The Court rejected this submission. Section 67WB(1) of the QBCC Act lists categories of building work not eligible for assistance under the Scheme and, in section 67WB(1)(f), expressly authorises regulations that exclude other types of building work. Nor was the regulation so lacking in reasonable proportionality that it was not a real exercise of power. The Court emphasised that the three-storey threshold reflects a policy choice made by Parliament and it is not for the courts to replace that choice with their own. Section 26(a) was therefore found to be valid.
CGC Qld Pty Ltd v Ziegel Co Pty Ltd [2026] QSC 224
Andrew Orford | Ren Shike | Ada Harvey
Key takeout
- Parties may ‘drift’ into a construction contract for the purpose of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act) through their conduct, even where no subcontract or novation is signed.
- A consistent course of dealings, including the performance of work, agreed rates and payment claims, may be enough to establish a contract, particularly where the parties have agreed how work is to be valued.
- Reference dates may be inferred by the parties’ dealings.
- An adjudicator has the power to decide whether further submissions requested by the adjudicator were properly made, including for example where the submissions are received after the deadline set by the adjudicator. Â
Facts
In July 2024, CGC Qld Pty Ltd (CGC) engaged Brizmasonry Pty Ltd (Brizmasonry) under a written subcontract to perform construction works.
In November 2024, Brizmasonry informed CGC that a related entity, Ziegel Co Pty Ltd ATF Norcott Family Trust (Ziegel), would perform the remaining works and sought CGC’s consent to novate the subcontract. Despite the proposed novation not being executed and no written subcontract being signed, Ziegel commenced and continued performing the works.
In February 2025, Ziegel provided CGC with a schedule of rates and requested a work order. CGC did not respond. Despite this, CGC paid or partly paid Ziegel’s payment claims for contract works and variation works in accordance with the schedule of rates over several months. Payment certificates issued by CGC identified Ziegel as the subcontractor, albeit noting that no signed subcontract existed.
On 29 August 2025, Ziegel issued a payment claim for $81,666. CGC did not pay the claim, following which Ziegel applied for adjudication under the BIF Act. The adjudicator determined the application in Ziegel’s favour awarding $79,531.
CGC applied to the Supreme Court of Queensland seeking declarations that the adjudication decision was void. CGC contended that:
- no construction contract existed between CGC and Ziegel;
- the payment claim was made before the relevant reference date; and
- the adjudicator committed jurisdictional error by considering further submissions that were not ‘properly made’ because they were lodged 24 minutes after the deadline the adjudicator had set.
Decision
Hindman J dismissed CGC’s application and upheld the adjudication decision in favour of Ziegel.
Construction contract existed
Her Honour found that a construction contract existed for the purposes of the BIF Act, notwithstanding the absence of a signed subcontract or executed novation. The test was whether there was a sufficiently concluded, bilateral state of affairs by the time of the payment claim. Ziegel performed the work at CGC’s request, and CGC paid four earlier claims calculated on Ziegel’s rates. That was at least an ‘other arrangement’ under s 64 of the BIF Act. Further, the parties had agreed how the work would be valued.
Payment claim made after the reference date
CGC’s argument that the payment claim was made before the relevant reference date was rejected. CGC’s automated reminders to submit claims before the 25th, and the parties’ course of dealing, established a reference date of the 25th of each month. The payment claim was validly made in respect of the 25 August 2025 reference date on 29 August 2025.
Adjudicator entitled to consider late submission
The Court also rejected the challenge to the adjudicator’s consideration of further submissions lodged 24 minutes out of time. Her Honour held that s 84(2) of the BIF Act empowers an adjudicator to request further submissions and prescribe the timeframe for their provision, while s 84(4) confirms that an adjudicator’s power to decide an application is not affected by a party’s failure to make a submission within time. Unlike statutory time limits, such as those that apply to applications and responses, a deadline for further submissions set by the adjudicator is not jurisdictional. Whether late submissions are ‘properly made’ (and so able to be considered under s 88(2)) is for the adjudicator to decide, and by considering the late further submissions, the adjudicator implicitly decided they were properly made.
Andrew Hales | Sannan Tariq | Alison Hwang
Key takeouts
- A principal that asserts a time bar in correspondence may still waive it, for example by asking the superintendent to determine the claim on its merits or by its representatives indicating that a variation request will follow. A ‘no waiver’ clause does not prevent waiver by conduct and is itself capable of being waived by conduct.
- A principal’s ‘reserve power’ to extend time in its absolute discretion does not displace the prevention principle. That power must still be exercised honestly and fairly, unless the clause also states that the principal is under no obligation to extend, or to consider whether to extend, time.
- Private communications between a principal and the superintendent undermine the superintendent’s role. An unqualified contractual right to replace the superintendent cannot be used to prevent a determination the principal does not want; doing so destroys the parties’ contractual bargain.
- A superintendent does not ordinarily owe a sophisticated, well-resourced contractor a duty of care for pure economic loss. The contractor’s practical recourse lies in contractual claims against the principal, and not in a negligence claim against the superintendent for breach of duty of care.
- Where the contract requires extension of time (EOT) assessments to disregard whether the contractor can still meet the date for practical completion, the contractor owns the float. But loss of non-critical ‘activity float’ alone does not justify an EOT or delay costs; only delay to practical completion counts.
- A delay cost clause covering ‘reasonable additional costs and expenses directly incurred’ by the contractor as a result of the delay extends to the contractor’s overheads and usual margin. A principal wishing to exclude overheads or margin from delay cost recovery must include clear drafting to that effect.
- Care is required when drafting EOT and programming clauses. Delay assessment methodologies (such as time impacted analysis) should be defined, and parties should expect that a genuine, bona fide revision to the construction program may displace the original baseline for delay analysis, even if the work is not ultimately carried out in accordance with the revised program.
Facts
In May 2020, Alinta Energy Transmission (Roy Hill) Pty Ltd (principal) and Clarke Energy (Australia) Pty Ltd (contractor) entered into a $78 million engineering, procurement and construction contract (contract) to build a new 60MW gas-fired power station in Western Australia (project). The initial date for practical completion was 9 March 2022. The superintendent granted an EOT to extend that date to 20 April 2022.
The Project experienced substantial delays arising from, among other things, existing underground services, the impacts of COVID-19, work within an operational power station and the principal’s failure to make the electricity network available for testing and commissioning. The contractor submitted claims seeking EOTs, delay costs and variations. The principal rejected the contractor’s claims and sought to recover approximately $7.8 million in liquidated damages for delay.
In April 2023, the contractor commenced proceedings in the Supreme Court of New South Wales, seeking EOTs, delay costs, payment of the disputed variation and relief from liquidated damages. It also pursued alternative Australian Consumer Law and estoppel claims concerning the principal’s pre-contractual representations, and negligence claims against the 3 people who had fulfilled the role of superintendent.
Decision
Rees J found substantially in favour of the contractor, granting it a 142-day EOT from the 168.5 days the contractor claimed and $7,192,414 plus interest. Her Honour extended the date for practical completion from 20 April 2022 to 9 September 2022, which significantly reduced the principal’s entitlement to liquidated damages. In reaching that conclusion, her Honour made a number of significant findings concerning the party responsible for removal of the underground services, waiver, the prevention principle, superintendent independence, float ownership, delay costs and delay analysis methodology. The key findings are discussed further below.
Underground services
The Court held that the principal, rather than the contractor, was responsible for removing existing underground services and reinstating the affected areas. The drafting of the contract, the pre-contractual discussions between the parties, and the assumptions mentioned in the contractor’s tender supported the conclusion that the principal was obliged to remove the underground services. The principal’s failure to do so was a compensable cause of delay and formed the foundation of the contractor’s successful EOT and delay cost claims in respect of EOT 1 and its corresponding relief from liquidated damages.
Australian Consumer Law and estoppel claims
The Court rejected the contractor’s misleading or deceptive conduct and estoppel claims concerning the principal’s pre-contractual representations about removing underground services. However, the contractor succeeded in estoppel in relation to its variation claim. Having directed the contractor to relocate its site amenities and indicated that a variation proposal would be requested, the principal was estopped from relying on the contractual requirement for a written variation order.
Waiver by conduct
Although the contractor had not strictly complied with the procedural requirements under the contract for EOT 1, which concerned delays arising from the principal’s failure to remove existing underground services, the Court found that the principal had waived its right to rely on that failure through its own conduct. This was because the contractual regime for handling EOT claims had broken down entirely, with none of the required timeframes for determination of the EOT claims being met.
Further, by asking the superintendent to determine EOT 1 on its merits, the principal acted inconsistently with the position it had maintained throughout its correspondence that EOT 1 should have been rejected outright.
The Court also found that a clause requiring waiver to be in writing did not stop a waiver arising from the principal’s conduct and that the requirement itself could be waived by conduct.
The prevention principle
In the alternative to waiver, the contractor argued that the principal’s acts of prevention required it to exercise its discretion to extend time.
The Court found that the prevention principle was not excluded by a clause of the Contract giving the principal absolute discretion to extend time. Although the clause permitted the principal to grant an extension for any reason, it did not expressly provide that the principal was under no obligation to extend time, or even to consider whether an extension should be granted. As a result, the principal was required to exercise its discretion honestly and fairly, having regard to the prevention principle.
Her Honour considered that the early stages of the project were marked by acts of prevention by the principal and held that, had the contractor not succeeded on waiver, the principal would have been required to exercise its discretion to extend time.
Limits on replacing a superintendent
The Court held that the principal could not rely on its apparently unqualified contractual right to replace the superintendent so as to prevent a determination it considered unfavourable to its interests.
Her Honour found that the second superintendent’s private communications with the principal, and the principal’s subsequent decision to replace him after he indicated that he was minded to issue a certificate of practical completion, undermined the superintendent’s independent role and the parties’ contractual bargain. Although the Contract permitted the principal to replace the superintendent at any time, that power was required to be exercised consistently with the principal’s implied duty to cooperate and did not extend to removing a superintendent simply because he was going to make a determination favourable to the contractor. The Court relied on these findings in its waiver analysis as further evidence that the principal had not adhered to the contractual EOT regime.
Superintendent’s duty of care
The Court dismissed the negligence claims brought by the contractor against each of the 3 superintendents personally because the contractor was not ‘vulnerable’ in the relevant sense. The contractor was a sophisticated, well-resourced commercial party which had legal assistance in drafting and negotiating the contract. Further, the contract itself provided the contractor with contractual recourse if the superintendent failed to perform its role properly.
Float ownership
The Court found that on a proper construction of the contract, the contractor owned the float in its program because the contract required EOT assessments to disregard whether the contractor could still achieve practical completion by the contractual completion date without an extension. However, the loss of ‘activity float’ on a non-critical activity did not establish the contractor’s entitlement to an EOT or delay costs. The contractor still had to show an actual delay to practical completion, since the contract’s EOT and delay costs provisions were tied to delay on the critical path to practical completion.
Delay costs include overheads and margin
The parties disputed the scope of a clause in the contract requiring the principal to pay the contractor ‘the reasonable additional costs and expenses directly incurred’ by the contractor as a result of compensable delay. In contrasting that formulation for a delay costs entitlement with different drafting considered in other judgments, the Court rejected the principal’s narrower interpretation that this wording was limited only to the contractor’s actual bare costs.
Her Honour concluded that where a delay was caused by an event the contractor did not cause and could not have avoided, it was commercially unrealistic to expect the contractor to pass on its costs to the principal without also recovering its overhead costs and usual margin under the wording of the delay costs clause considered in this case. On that basis, the Court allowed the contractor’s claimed labour rates (inclusive of margin), a 15% contractor margin on flights, accommodation, and equipment hire, and the cost of extending bank guarantees.
Extension of time and delay costs methodology
The Contract required the effects of an ‘extension event’ to be assessed using a ‘time impacted analysis’ but did not define that term. The Court adopted the description in the Society of Construction Law’s Delay and Disruption Protocol, which explains that time impacted analysis assesses the effect of a delay event using a prospective approach, assessing the effect of the delay event on the contractor’s intentions for the future conduct of the work, in light of the progress actually achieved at that time.
The Court further held that a genuine revision to the construction program may show that an earlier baseline program was not reasonable, achievable, or appropriate. In such a case, the baseline program was not to be relied on for a time impacted analysis, regardless of whether the work was ultimately carried out in accordance with the revised program. Here, the revision remained in place for 6 to 12 months and followed safety workshops and consultation with the principal, rather than being made to inflate the effect of a delay event.
Practical implications
For principals, the decision highlights the importance of administering contracts consistently with the positions taken under them. Principals should be cautious when relying on contractual time bars, refusing to exercise discretionary EOT powers, or interacting with superintendents, as conduct may undermine otherwise available contractual rights.
For contractors, the decision demonstrates that relief may still be available notwithstanding non-compliance with contractual procedures where a principal’s conduct is inconsistent with strict enforcement. The case also reinforces the importance of carefully documenting delay events, variation instructions and the factual basis for EOT and delay cost claims.
Malligan v Chevron Apartments Pty Ltd; Cantavenera v Chevron Apartments Pty Ltd [2026] QSC 195
Julie Whitehead | Olivia Doonan | Max Rylance
Key takeouts
- Unless the contract clearly provides otherwise, a party cannot rely on its own breach to obtain a contractual benefit, including a right to terminate.
- A court will not read down an unambiguous obligation merely to produce a more harmonious or commercially convenient contract.
- If a developer wishes to retain a termination right where its own failure has caused the sunset date to pass, this must be expressly provided for in the contract.
Facts
In 2021, Chevron Apartments Pty Ltd (Chevron) entered into two off-the-plan contracts for apartments in the Chevron One development on the Gold Coast.
Clause 10.2 provided that, subject to Chevron’s express termination rights under clause 16 and the buyers paying the balance of the purchase price at settlement, Chevron ‘must establish the Scheme, register the Plan and effect Settlement’ by the relevant 5-year sunset date.
Clause 16 gave Chevron wide termination rights, including if it decided not to proceed because of finance, insufficient sales, increased construction costs or other viability concerns. However, Chevron could only exercise most of its rights if it also terminated every other contract in the scheme.
In 2026, after the sunset date passed without settlement, Chevron purported to terminate the contracts. Under the contracts Chevron had a reciprocal right to terminate during any period in which a buyer was entitled to terminate under the Body Corporate and Community Management Act 1997 (Qld) (BCCM Act). Section 271B of the BCCM Act gives a buyer a right to terminate if the seller has not settled by the sunset date. At the time of the purported termination, construction of the apartments appeared largely complete.
The buyers challenged the terminations, arguing that Chevron could not rely on its own failure to effect settlement by the sunset date under clause 10.2.
Decision
Freeburn J ruled in favour of the buyers and declared both contracts valid and binding. The Court held that clause 10.2 imposed a clear obligation on Chevron to establish the scheme, register the plan and effect settlement by the sunset date, subject only to the qualifications expressed in that clause.
The plain meaning of clause 10.2 prevails
The Court held that the words ‘must establish the Scheme, register the Plan and effect Settlement … by the Sunset Date’ were unambiguous and susceptible of only one meaning. A reasonable businessperson would understand them as imposing an obligation on Chevron to establish the scheme, register the plan and effect settlement by the sunset date.
Chevron argued that clause 10.2 should be read down (at most, to an implied obligation to use reasonable efforts) by harmonising the contracts as a whole and having regard to the statutory context and uncertainty created by the COVID-19 pandemic when the contracts were made. The Court rejected that approach. A search for contractual ‘harmony’ could not displace the ordinary meaning of clear language. The Court doubted that a reasonable-efforts term could be implied from the word ‘must’ used in clause 10.2. The uncertainty of the COVID-19 era did not provide a proper explanation for reading down clause 10.2.
The Court also held that the words ‘subject to clause 16’ in clause 10.2 were significant. Those words preserved Chevron’s extensive termination rights. Chevron could therefore still decide not to proceed with the contracts if, for example, construction costs rose or the project became unviable.
Chevron could not take advantage of its own breach
The Court applied the general rule of construction that, absent a clear provision to the contrary, the parties are presumed not to intend that one party may obtain a contractual benefit from its own breach. The contract did not expressly authorise Chevron to rely on its breach of clause 10.2 to terminate. Because Chevron’s own failure to settle by the sunset date was the event on which it sought to rely, the right to terminate was unavailable.
No material prejudice under section 214
Separately, Chevron argued that changes to the development materially prejudiced the buyers, giving them termination rights under section 214 of the BCCM Act, which in turn gave Chevron a reciprocal right to terminate. Section 214 of the BCCM Act gives a buyer the right to terminate a contract when variations to a development’s disclosure statement cause material prejudice to the buyer. The buyers denied any prejudice. The Court assessed prejudice objectively, having regard to the particular buyer’s circumstances. The Court noted that there must be a causal and proportionate relationship between the inaccuracy and the prejudice, and the buyer must be disadvantaged substantially or to an important extent.
The evidence did not establish that ongoing construction or increased body corporate contributions materially prejudiced either buyer. A reservation of the right to deliver later stages ‘at any time’ was not evidence that construction would continue for long. An increase in contributions of about 40% (roughly $2,100 to $2,250) was not material in the context of the contracts. The Court admitted the buyer’s evidence comparing levies at a nearby unit as a relevant market reference point. The buyers’ subjective views, and any increase in the market value of the units, were irrelevant to the statutory test.
Plus500AU Pty Ltd v AghaeiRad [2026] FCAFC 125
Tom French | Shevaun Stringer | Naoisa McNelis
Succar v Dominium Homes Pty Ltd [2026] NSWSC 1117
Andrew Hales | Luke Sundercombe | Alison Hwang
TQM Design & Construct Pty Ltd v East End Stage 2 Pty Ltd [2026] NSWSC 1032
Andrew Hales | Andrew Clark  | Isabella Greenhalgh
Alliance Living Pty Ltd v Arch-System Fabrication Pty Ltd [2026] NSWCA 157
Andrew Hales | Luke Sundercombe | Michael Sywak |  Zachary O’Hara
Sedl Earthmoving Pty Ltd v Nortask Pty Ltd [2026] QDC 98
Sarah Ferrett | Stephanie Murphy | Joseph Ryan
Genuity Pty Ltd v IG Power (Callide) Ltd [2026] QSC 194
David Pearce | Hazal Gacka | Lois Min
Rainmont Pty Ltd (in liquidation) v Seymour Whyte Constructions Pty Ltd [2026] QSC 125
Sarah Ferrett |Â Sarah Cahill |Â Max Rylance
York Property Holdings Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd [2026] QSC 156
Sian Keast |Â Matt Hammond |Â Sarah Nichols
Co-operative Bulk Handling Ltd (ABN 29 256 604 947) v Martinus Rail Pty Ltd [2026] WASCA 82
Tom French  | Sasha Thomas | Helen Do
Reward Interiors Pty Ltd t/s Reward Group v Tackelly No 8 Pty Ltd atf Tackelly No 8 Trust [2026] NSWCA 133
Tom French | Briony Whyte | Sasha Thomas | Helen Do
Bata v Pathik & Ors [2026] VSCA 138
Isobel Carmody | Joan Wu | Harley Stephens
Tomkins Commercial & Industrial Builders Pty Ltd v Starline Interiors Pty Ltd [2026] QSC 21
Sian Keast | Olivia Doonan | Siobhan Beckett
York Property Holdings Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd [2026] QCA 63
David Pearce | Allie Flack | Max Rylance
Ipswich Earthmoving Machinery Pty Ltd v Austral Bricks (Qld) Pty Ltd & Ors [2026] QDC 26
Julie Whitehead | Elissa Morcombe | Joseph Ryan
Built Pty Ltd v Victorian Correctional Infrastructure Partnership Pty Ltd [2026] VSC 76
Chris Hey | Michael Lo | Joan Wu
McCallum v Projector Films Pty Ltd [2026]FCA 173
Ben Fuller | Vanessa McBride | Elizabeth Harris
The Star Entertainment Sydney Properties Pty Ltd v Buildcorp Group Pty Ltd [2026] NSWSC 27
Andrew Hales | Luke Sundercombe | Ersen Ahmet
L.U. Simon Builders Pty Ltd v Cardigan Commercial Pty Ltd (No 2) [2026] VSC 33
Chris Hey | Michael Lo | Andre Liacos
York Property Holdings Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd & Ors [2025] QSC 286
David Pearce | Stephanie Murphy | Siobhan Beckett
Taringa Property Group Pty Ltd v Kenik Pty Ltd [2025] QSC 222
Andrew Orford | Laura Berry | Jazmin Sherrington
Cooper & Oxley Group Pty Ltd v Koitka [2026] WASC 4
Tom French | Shevaun Stringer | Naoisa Mcnelis
CPB Contractors Pty Ltd & Ors v MSS Projects (NSW) Pty Ltd t/as MSS Steel & Ors [2025] QSC 239
Julie Whitehead | Ren Shike | Ada Harvey
Platform Constructions Pty Ltd v Fourth Dimension Au Pty Ltd [2025] QCA 264
Sarah Ferrett | Matt Hammond | Jazmin Sherrington
Shamrock Civil Engineering Pty Ltd v Cleanaway Solid Waste Pty Ltd [2025] QCA 178
Michael Creedon | Megan Sharkey | Oliver Conroy
Cobolt Constructions Pty Ltd v Duke Ventures Wellington Street Pty Ltd [2025] VSC 609
Chris Hey | Michael Lo | Isabella Nicolaci
Kumar v Frankies Cranes Pty Ltd [2025] NSWSC 1264
Ben Fuller | Andrew Black | Elizabeth Harris
JTS Trading Group Pty Ltd v Allroads Pty Ltd (in liq) [2025] QSC 211
Michael Creedon | Clare Turner | Gabriela Roworth
Downer EDI Rail Pty Ltd v DT Infrastructure Pty Ltd [2025] QSC 212
Sian Keast | Stephanie Murphy | Charlotte Kath
Tomkins Commercial & Industrial Builders Pty Ltd v Starline Interiors Pty Ltd [2025] QSC 226
Sarah Ferrett | Hazal Gacka | Oliver Conroy
Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161
Andrew Hales | Rachel Cheung | Isabella Waters
Grounded Construction Group Pty Ltd v KW Civil & Construction Pty Ltd [2025] WASC 307
Tom French | Shevaun Stringer | Sasha Thomas
Bridgeman Agencies Pty Ltd v S.E. QLD Plumbing & Drainage Pty Ltd [2025] QSC 167
Andrew Orford | Olivia Doonas | Rose Dillon
Cagney v D&J Building Contractors Pty Ltd [2025] QCA 116
David Pearce | Charlotte Gordon | Jack Gibney
WNA Construction Pty Ltd v Canberra Building and Maintenance Pty Ltd [2025] ACTCA 17 (4 June 2025)
Ben Fuller | Andrew Black | Elizabeth Harris
Manariti Plumbing Pty Ltd v Universal Property Group Pty Ltd [2025] NSWCA 135
Andrew Hales | Anique Mawa | Conor Bates
Bright Days Herston Pty Ltd v ATG Project & Property Solutions Pty Ltd [2025] QSC 147
Michael Creedon | Elissa Morcombe | Charlotte Kath
The Owners – Strata Plan No 93543 v Zhang (No 3) [2025] NSWSC 571
Andrew Hales | Luke Sundercombe | Ersen Ahmet
Baguley Build Pty Ltd v Olcon Concrete & Construction Pty Ltd & Anor [2025] QSC 126
Julie Whitehead | Laura Berry | Rose Dillion
The Owners – Strata Plan 82089 v Omaya Holdings Pty Ltd (No 3) [2024] NSWSC 1511
Andrew Hales | Anique Mawa | Conor Bates
The Owners Corporation SP 90832 v Dyldam Developments Pty Ltd [2024] NSWSC 1519
Andrew Hales | Michelle Knight | Jenny Lin
York Property Holdings Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd [2025] QCA 39
David Pearce | Sarah Cahill | Jack Gibney
Procon Developments (Australia) Pty Ltd v Hi-Cal Bricklaying [2025] QSC 67
Sian Keast | Allie Flack | Jack Gibney
Pacific Diamond 88 Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd [2025] QCA 50
Michael Creedon | Luke Trimarchi | Charlotte Kath
Forme Two Pty Ltd v McNab Developments (Qld) Pty Ltd [2025] QSC 96
Sarah Ferrett | Ren Shike | Charlotte Kath
Allen & Anor v Contrast Constructions Pty Ltd [2025] QSC 18
Julie Whitehead | Alexandria Hammerton | Rose Dillon
York Property Holdings Pty Ltd v Tomkins Commercial Industrial Builders Pty Ltd [2025] QSC 44
David Pearce | Sarah Cahill | Jack Gibney
Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 327
Andrew Orford | Laura Berry | Jazmin Sherrington
Viasat Inc v Hansen Yuncken Pty Ltd [2024] NSWSC 1581
Andrew Hales | Laura-Rose Lynch | Cedric Barakat
Merkon Constructions Pty Ltd v Residence Company Pty Ltd [2025] VSC 151
Chris Hey | Michael Lo | Meg Reid
Re Roberts Construction Group Pty Ltd [2024] VSC 679
Chris Hey | Michael Lo | Millie Lewis
Taringa Property Group Pty Ltd v Kenik Pty Ltd [2024] QSC 298
Andrew Orford | Laura Berry | Max Rylance
Sovereign Building Company Pty Ltd v Sheehan Group Pty Ltd [2025] WASC 11
Tom French | Penny Bond | Naoisa McNelis
Shamrock Civil Engineering Pty Ltd v Honan Insurance Group Pty Ltd [2024] QSC 313
Michael Creedon | Megan Sharkey | Jazmin Sherrington
John Holland Queensland Pty Ltd v SecureFence Pty Ltd [2024] QSC 290
Julie Whitehead | Ren Shike | Siobhan Beckett
Crystele Designer Homes Pty Ltd v Wood [2024] NSWSC 1438
Andrew Hales | Karen Hanigan | Sean Cooley
Roberts Construction Group Pty Ltd v Drummond Carpentry Services Pty Ltd [2024] VSC 246
Nikki Miller | Isobel Carmody | Madeleine Matkowsky
Venture Spirits Pty Ltd v Adjudicate Today Pty Ltd [2024] TASSC 12
Nikki Miller | Isobel Carmody | Isabella Nicolaci
RE Oakey Pty Ltd v Canadian Solar Construction (Australia) Pty Ltd [2024] QCA 202
Sarah Ferrett | Matt Hammond | Jazmin Sherrington
Platform Constructions Pty Ltd v Fourth Dimension Au Pty Ltd ATF BD Hope Unit Trust & Ors [2022] QSC
Andrew Orford | Sarah Cahill | Joseph Ryan
Chevron Park Pty Ltd v Groupline Constructions Pty Ltd & Ors [2024] QSC 202
David Pearce | Alexandria Hammerton | Jazmin Sherrington
Pafburn Pty Limited v The Owners – Strata Plan No 84674 [2024] HCA 49
Claire Tait | Maciej Getta | Luke Sundercombe
Paladin Projects Pty Ltd v Visie Three Pty Ltd & Ors [2024] QSC 230
Sian Keast | Matt Hammond | Siobhan Beckett
Colormode Pty Ltd v Civic Construction Group Pty Ltd [2024] QDC 148
Michael Creedon | Clare Turner | Siobhan Beckett
Binah Constructions Pty Ltd v PTMG Pty Ltd [2024] NSWSC 872
Claire Tait | Laura-Rose Lynch | Nicole Sawick
Drummond v Gordian Runoff Limited ACN 052 179 647 [2024] NSWCA 239
Claire Tait | Harkiran Kaur | Daphne Zhou
Hestbay Pty Ltd v One Sector Pty Ltd [2024] QSC 180
Sarah Ferret | Megan Sharkey | Max Rylance
SFP Events Pty Ltd v Little Swamp II, Inc & Anor [2024] QSC 132
Andrew Orford | Petrina Macpherson | Abhishek Rishi
OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310
Tom French |Â Penny Bond |Â Alicia Harries
Glasson and McLean [2024] WASAT 96
Tom French | Penny Bond | Lara Solomon
Whitaker v F.P & H.S Keogh Pty Ltd (Building and Property) [2024] VCAT 708
Chris Hey | Michael Lo | Stacey CloughÂ
LHRE Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WADC 61
Tom French | Penny Bond | Alicia Harries
Lendlease Building Pty Ltd v BCS Airport Systems Pty Ltd & Ors [2024] QCS 164
Julie Whitehead | Laura Berry | Tara Vele
The Owners – Strata Plan 99960 v SPS Building Contractors Pty Ltd [2024] NSWSC 687
Andrew Hales | Sophie Wallwork | Emily Miers
EnerMech Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd 2024 NSWCA 162
Andrew Hales | Maciej Getta | Cedric Barakat
Bright Days Herston Pty Ltd v ATG Project & Property Solutions Pty Ltd [2024] QSC 94
Michael Creedon | Matt Hammond | Tara Vele
Body Corporate for the Johnson CTS 49098 v Maxcon Constructions Pty Ltd [2024] QSC 65
Julie Whitehead | Renee Shike | Connor Wright
Newstart Homes Australia Pty Ltd v Kodiak Concrete Pty Ltd [2024] QSC 129
David Pearce | Allie Flack | Connor Wright
Mallonland Pty Ltd v Advanta Seeds Pty Ltd [2024] HCA 25
Andrew Orford  | Petrina Macpherson | Connor Wright
Andrew Orford | Elissa Morcombe | Abhishek Rishi
Stewart v Sherridon Pty Ltd [2024] VCC 1023
Chris Hey | Michael Lo | Stacey Clough
Samco Steel & Precast Pty Ltd v Roxton Commercial Builders Pty Ltd [2024] VCC 783 Â
Chris Hey | Isobel Carmody | Courtenay Wood
Deshmukh v Distinctive Building Services Pty Ltd [2024] WASAT 62
Tom French | Penny Bond | Alicia Harries
Makland Constructions Pty Ltd v Page Steel Fabrications Pty Ltd [2024] VSCA 142
Chris Hey | Michael Lo | Jesse Guo
Hanson Construction Materials Lty Ltd v Decmil Australia Pty Ltd [2024] VSC 361
Chris Hey | Michael Lo | Jasmine Reilly
The Owners – Strata Plan No 64757 v Sydney Remedial Builders Pty Ltd [2024] NSWCA 85
Andrew Hales | Karen Hanigan | Jenny Lin
Hino Group Pty Ltd v Singh and Anor [2024] NSWDC 124
Andrew Hales | Karen Hanigan | Jasper Choi
Metricon Homes Pty Ltd as trustee for Metricon Homes Unit Trust v Lipari [2024] NSWSC 566
Andrew Hales | Maciej Getta | Luke Sundercombe
Sun Engineering (Qld) Pty Ltd v Ravenswood Gold Pty Ltd [2024] QSC 68
Tom French | Penny Bond | Alicia Harries
Iris Broadbeach Business Pty Ltd v Descon Group Australia Pty Ltd & Anor [2024] QSC 16
Andrew Orford | Luke Trimarchi | Jarryd Cox
Andrew Orford | Laura Berry | Tara Vele
Ingeteam Australia Pty Ltd v Susan River Solar Pty Ltd [2024] QSC 30
Michael Creedon | James Knell | Connor Wright
Nepean Conveyors Pty Ltd and Linkforce Industrial Services Pty Ltd [2024] WASC 71
Tom French | Shevaun Stringer | Sasha Thomas
McDonald v MAK Constructions and Building Services Pty Ltd [2024] NSWCA 63
Andrew Hales | Karen Hanigan | William Vu
The Owners – Strata Plan No. 85494 v PBS Building (NSW) Pty Ltd [2024] NSWSC 381
Andrew Hales | Sophie Wallwork | Cedric Barakat
Karam Group Pty Ltd ATF The Karam (No. 1) Family Trust v HCA Queensland Pty Ltd & Ors [2024] QSC 34
Julie Whitehead | Alexandria Hammerton | Abhishek Rishi
Allen & Anor v Queensland Building and Construction Commission [2024] QCA 24
David Pearce | Megan Sharkey | Lochlan Andrew
Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd [2023] NSWCA 305
Andrew Hales | Maciej Getta | Jenny Lin
Sunshine East Pty Ltd v CBEM Holdings Pty Ltd [2023] NSWSC 744
Andrew Hales | Jessica Nesbit | Heidi Knights
Thurin v Krongold Constructions (Aust) Pty Ltd [2024] VSC 42
Nikki Miller | Isobel Carmody | Morsaal Aimaq
Taycon Pty Ltd v Williams [2023] QSC 297
David Pearce | Gemma Osborne | Jarryd Cox
Eastbound Estate Pty Ltd v DC Consolidated Investments Pty Ltd [2024] VSC 40
Nikki Miller | Isobel Carmody | Jack Holmes
Centurion Australia Investments Pty Ltd v APM Group (Aust) Pty Ltd [2023] VSCA 324
Nikki Miller | Isobel Carmody | Morsaal Aimaq
Shunshunli Pty Ltd v Seascape Constructions Pty Ltd [2023] VSC 725
Nikki Miller | Michael Lo | Henry Chesterman
Re Dask Entertainment Melbourne Pty Ltd [2023] VSC 660
Nikki Miller | Michael Lo | Morsaal Aimaq
Queensland Building and Construction Commission v Grenier Developments Pty Ltd & Anor [2024] QDC 6
Michael Creedon | Allie Flack | Aidan Kleynhans
City of Port Phillip v Shout Rock Cafes Pty Ltd [2023] VSCA 327
Peter Wood |  Isobel Carmody  | Xavier Vale
Vantralia Pty Ltd v Redline Water Infrastructure Pty Ltd [2023] QSC 291
Andrew Orford | James Knell |  Lochlan Andrew
Thallon Mole Group Pty Ltd v Morton; Morton v Thallon Mole Group Pty Ltd [2023] QCA 250
Andrew Orford | Sarah Cahill | Jarryd Cox
Canadian Solar Construction Pty Ltd v Re Oakey Pty Ltd [2023] QSC 288
Sarah Ferrett | Matt Hammond | Lochlan Andrew
ESR Investment Management 2 (Australia) Pty Limited v AllRoads Pty Ltd [2023] QSC 235
Michael Creedon | Laura Berry | Aidan Kleynhans
Descon Group Australia Pty Ltd v 35 Merivale Pty Ltd [2023] QSC 276
Sian Keast | Mark Wheelahan | Aidan Kleynhans
Quilkey & Anor v Tractile Combined Pty Ltd & Ors [2023] QDC 204
Sian Keast | Sarah Cahill | Jarryd Cox
The Owners – Strata Plan No 84674 v Pafburn Pty Ltd [2023] NSWCA 301
Andrew Hales | Maciej Getta | Luke Sundercombe
Turnkey Innovative Engineering Pty Ltd v Witron Australia Pty Ltd [2023] NSWSC 981
Andrew Hales | Michelle Knight | Sarah Summers
H & M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd (No 4) [2023] NSWSC 925
Andrew Hales | Maciej Getta | Ersen Ahmet
Karam Group Pty Ltd ATF The Karam (No. 1) Family Trust v HCA Queensland & Ors [2023] QSC 245
Andrew Orford | Gemma Osborne | Aidan Kleynhans
we-do-IT Pty Ltd v we-do-IT-Inc [Delaware] [2023] VSC 611
Andrew Orford | Isobel Carmody | Aria Saffar
Niclin Constructions Pty Ltd v Robotic Steel Fab Pty Ltd & Anor [2023] QSC 218
David Pearce | Petrina Macpherson | Jarryd Cox
Qantas Airways Limited & Anor v BMD Constructions Pty Limited [2023] QSC 206
Andrew Orford | Alex Hammerton | Aidan Kleynhans
Andrew Hales |  Laura-Rose Lynch | Luke Sundercombe
Karam Group Pty Ltd ATF The Karam (No. 1) Family Trust v HCA Queensland Pty Ltd & Ors [2023] QSC 212
Sarah Ferrett | Matt Hammond | Lochlan Andrew
Springfield City Group Pty Ltd v PIPE Networks Pty Ltd [2023] QCA 172
Michael Creedon | Allie Flack | Samuel O’Loughlin
Seymour & Anor v Drill Engineering & Pastoral Company Pty Ltd [2023] QCA 159
David Pearce | Elissa Morcombe | Spencer Hayward
Diamond Builders Pty Ltd v Gilridge Investments Pty Ltd [2023] VCC 1527
Peter Wood | Isobel Carmody | Sarah Waring
Schott AG v Melton Willows Pty Ltd [2023] VSC 364
Nikki Miller | Michael Lo | Courtenay Wood
Krongold v Thurin [2023] VSCA 191
Peter Wood | Jeanette Barbaro | Isobel Carmody | Joseph Xuereb
Drake Constructions Vic Pty Ltd v Three Construct Group Pty Ltd [2023] VCC 1325
Nikki Miller | Isobel Carmody | Sean Bricknell
Hawkesdale Asset Pty Ltd v Bennett [2023] VSC 409
Nikki Miller | Michael Lo | Millie Lewis
PHHH Investments v United Commercial Projects Pty Ltd [2023] VCC 516
Nikki Miller | Michael Lo | Millie Lewis
Endeavour Constructions Pty Ltd v Down Under Piling Australia Pty Ltd [2023] VSC 424
Nikki Miller  | Michael Lo  | Henry Chesterman
Parkview Constructions Pty Ltd v The Owners – Strata Plan No 90018 [2023] NSWCA 66
Andrew Hales | Michelle Knight | Brigida Johns
Marques Group Pty Ltd v Parkview Constructions Pty Ltd [2023] NSWSC 625
Andrew Hales | Karen Hanigan | Brigida Johns
Veesaunt Property Syndicate 1 Pty Ltd v Alliance Building and Construction Pty Ltd [2023] QSC 129
Sian Keast | Megan Sharkey | Samuel O’Loughlin
King River Digital Assets Opportunities SPC v Salerno [2023] NSWSC 510
Andrew Hales | Chris Hey | Isobel Carmody
Total Construction Pty Ltd v Catholic Healthcare Limited [2023] NSWSC 585
Andrew Hales | Karen Hanigan | Sean Cooley
Schrader v David Broach trading as David Broach Building Services [2023] NSWDC 97
Andrew Hales | Mark Glynn | Tom Lawler
Reeves v Alt Advisory (Jersey) Limited and Alt Financial Group Limited [2023] VSC 249
Nikki Miller | Chris Hey | Isobel Carmody | Phillip Martin
Factory X Pty Ltd v Gorman Services Pty Ltd [2023] VSC 247
Nikki Miller | Chris Hey | Jacob Broderick
GCB Constructions Pty Ltd v SEQ Formwork Pty Ltd & Ors [2023] QSC 71
Michael Creedon | James Knell | Spencer Hayward
Insite Construction Services Pty Ltd v Daniels Civil Pty Ltd & Anor [2023] QSC 33
Sarah Ferrett | Luke Trimarchi | Joey Henthorn
Kingdom of Spain v Infrastructure Services Luxembourg S.Ã .r.l [2023] HCA 22
Andrew Orford  | Andrew Hales |  Chris Hey  |  Isobel Carmody
SLIC B&D Pty Ltd v David Trinder [2023] WASAT 1
Tom French | Penny Bond | Charlie Clifton
Downer EDI Works Pty Ltd v Steensma [2022] WASC 396
Tom French | Charlie Clifton | Penny Bond
Strata Plan 99576 v Central Construct Pty Ltd [2023] NSWSC 212
Andrew Hales | Max Ababio | Hannah Hurst
Allencon Pty Ltd v Palmgrove Holdings Pty Ltd trading as Carruthers Contracting [2023] QCA 6
Andrew Orford | Sarah Cahill | Ali Harris
The Owners-Strata Plan 86807 v Crown Group Constructions Pty Ltd [2023] NSWSC 44
Andrew Hales | Michelle Knight | Luke Sundercombe
The Owners – Strata Plan No 90018 v Parkview Constructions Pty Ltd [2022] NSWSC 1123
Andrew Hales | Michelle Knight | Jaime Parker
J Hutchinson Pty Ltd v Transcend Plumbing and Gasfitting Pty Ltd [2023] VSC 39
Nikki Miller | Isobel Carmody | Xavier Vale
BCFK Holdings Pty Ltd v Rork Projects Pty Ltd [2022] NSWSC 1706
Andrew Hales | Laura-Rose Lynch | Jack McFadden
The Owners – Strata Plan No 84674 v Pafburn Pty Ltd [2023] NSWSC 116
Andrew Hales | Michelle Knight | Heidi Knights
Building Legislation Amendment (Building Classes) Regulation 2023
Carrie Metcalfe | Andrew Hales | Jeanette Barbaro
CBI Constructors Pty Ltd v Chevron Australia Pty Ltd [2023] WASCA 1
Tom French | Penny Bond | Alicia Harries
Built Qld Pty Limited v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [2022] QCA 266
Michael Creedon | Allie Flack | Ali Harris
Andrew Hales | Maciej Getta | Luke Sundercombe
Roberts v Goodwin Street Developments Pty Ltd [2023] NSWCA 5
Andrew Hales | Mark Glynn | Joel Dueck
In the matter of Nicolas Criniti Pty Ltd (in Liquidation) [2022] NSWSC 1149
Andrew Orford | Laura Berry | Mikayla Colak
Andrew Hales | Sophie Wallwork | Tom Lawler
Ser Kim Koi v GTMS Construction Pte Ltd and others and another appeal [2022] SGHC(A) 34
Andrew Hales | Laura-Rose Lynch | James Pelosi
McNab Building Services Pty Ltd v Demex Pty Ltd [2022] NSWSC 1441
Julie Whitehead | Matt Hammond | Eva Squire
Devine Constructions Pty Ltd v Stowe Australia Pty Ltd & Ors (No 2) [2022] QSC 272
Demex Pty Ltd v John Holland Pty Ltd [2022] QSC 259
Andrew Orford | Petrina Macpherson | Keira Takacs
Gold Property Partners Pty Ltd v Dudzik & Anor [2022] QDC 245
Michael Creedon | Elissa Morecombe | Claudia Lizzio
Thurin v Krongold Constructions (Aust) Pty Ltd [2022] VSCA 226
Jeanette Barbaro | Isobel Carmody | Morsaal Aimaq
Piety Constructions Pty Ltd v Hville FCP Pty Ltd [2022] NSWSC 1318
Andrew Hales | Karen Hanigan | Heidi Knights
Boulus Constructions Pty Ltd v Warrumbungle Shire Council (No 2) [2022] NSWSC 1368
Andrew Hales | Laura-Rose Lynch | William Vu
Treasury Laws Amendment (More Competition, Better Prices) Act 2022 (Cth)
Michael Creedon | Eva Squire | Keira Takacs
Thomas Barnes & Sons PLC v Blackburn with Darwen Borough Council [2022] EWHC 2598 (TCC)
Nikki Miller | Sophie Wallwork
DBL Space Pty Ltd v Clynder Pty Ltd [2022] QSC 193
Julie Whitehead | Laura Berry | Claudia Lizzio
O’Rourke v Beechwood Homes (NSW) Pty Ltd [2022] NSWCATCD 116
Andrew Hales | Anique Mawa | Nicole Sawick
Addinos Pty Ltd v OJ Pippin Homes Pty Ltd [2022] QDC 205
Clare Turner | Luke Trimarchi | Mikayla Colak
Keegan v Ballast Point Pty Ltd [2022] NSWCA 179
Andrew Hales | Sophie Wallwork | James Pelosi
Denbrook Constructions Pty Ltd v CBO Developments Pty Ltd [2022] QDC 184
Sarah Ferrett | Alexandria Hammerton | Renee Shike
Lee v Lin & Anor [2022] QCA 140
Sian Keast | James Knell | Yibing Mao
Mineralogy Pty Ltd v Adani Mining Pty Ltd [2022] QDC 154
Andrew Orford | Matt Hammond | Eva Squire
Quilkey & another v Tractile Combined Pty Ltd & others [2022] QDC 185
Michael Creedon | Hazal Gacka | Zariyah Ahmed
MotionX Pty Ltd V Evok3d.com Pty Ltd [2022] QDC 124
Mark Wheelahan | Sarah Cahill | Zariyah Ahmed
SPEL Environmental Pty Ltd v IES Stormwater Pty Ltd [2022] FCA 891
Andrew Hales | Laura-Rose Lynch | Naomi Graham
The Owners – Strata Plan No 84674 v Pafburn Pty Ltd (No 2) [2022] NSWSC 1002
Andrew Hales | Sophie Wallwork | Jaime Parker
Paradise Outdoor Building Company Pty Ltd v Steward [2022] QCA 118
Michael Creedon | Laura Berry | Renee Shike
Drill Engineering & Pastoral Company Pty Ltd v Seymour & another [2022] QDC 1361
Julie Whitehead | Elissa Morcombe | Eva Squire
Demex Pty Ltd v Marine Civil Contractors Pty Ltd & Anor [2022] QSC 141
Andrew Orford | Petrina Macpherson | Alisha McGrady
Paridaen & Anor v Mahaside Pty Ltd [2022] QSC 109
David Pearce | Sam Rafter | Yibing Mao
Damon’s Earthworks Pty Ltd v AA Machinery Pty Ltd [2022] QDC 123
Michael Creedon | Alexandria Hammerton | Alisha McGrady
Look Design and Development Pty Ltd v Edge Developments Pty Ltd & Flaton [2022] QDC 116
Michael Creedon | Hazal Gacka | Alisha McGrady
Enco Precast Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union & Ors [2022] QCA 94
Deanna McMaster | Allie Flack | Renee Shike
Lendlease Pty Ltd v Owners Corporation No 11 PS526704E & Ors [2022] VSCA 105
Jeanette Barbaro | Tom Kearney | Michael Lo | Sean Bricknell
Graham & Anor v Alic & Anor [2022] QDC 106
Andrew Orford | Allie Flack | Eva Squire
Toohey v Golder & Ors (No. 2) [2022] QSC 93
David Pearce | Matt Hammond | Renee Shike
Allencon Pty Ltd v Palmgrove Holdings Pty Ltd [2022] QDC 90
Andrew Orford | Petrina MacPherson | Eva Squire
BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia Pty Ltd [2022] NSWCA 82
Andrew Hales | Tom Kearney | Isobel Carmody
The Owners – Strata Plan No 84674 v Pafburn Pty Ltd [2022] NSWSC 659
Andrew Hales | Sophie Wallwork | Will Ryan
Devine Constructions Pty Ltd v Stowe Australia Pty Ltd & Ors [2022] QSC 51
Julie Whitehead | James Knell | Zariyah Ahmed
Ruhle v Lormist Pty Ltd [2022] QCAT 100
Andrew Orford | Alexandria Hammerton | Eva Squire
Widdows v Pacific Blue Painting Pty Ltd & Anor [2022] QCAT 114
Clare Turner | Sam Rafter | Yibing Mao
Disley v Mount Emerald Wind Farm Pty Ltd & Anor (No 2) [2022] QSC 54
Julie Whitehead | Luke Trimarchi | Alisha McGrady
Queensland Building Corporation Commission v Kouzmenkov [2022] QDC 81
Michael Creedon | Megan Sharkey | Zariyah Ahmed
Concrib Pty Ltd v Cumner Contracting [2022] QSC 50
Sarah Ferrett | Sarah Cahill | Renee Shike
Jones and Anor v Rutch Constructions Pty Ltd [2022] QCAT 82
David Pearce | Hazal Gacka | Yibing Mao
CJM Innotrack Pty Ltd v Liang & Wang [2022] QCAT 53
Andrew Orford | Matt Hammond | Nikole Rabeling
Lanskey Constructions Pty Ltd v Westrac Pty Ltd [2022] WASC 90
Tom French | Penny Bond | Conor McCavana
Building and Other Legislation Amendment Bill 2022 (Qld)
Michael Creedon | Zariyah Ahmed
Niclin No 1 Pty Ltd v Lambert 66 Pty Ltd [2022] QDC 45
Andrew Orford | Allie Flack | Eva Squire
Renbar Constructions Pty Ltd v Sader [2022] NSWSC 172
Andrew Hales | Laura-Rose Lynch | William Vu
Forte Sydney Construction Pty Ltd v N Moit & Sons (NSW) Pty Ltd [2021] NSWDC 673
Andrew Hales | Maciej Getta | Taris Watson
Equa Building Services Pty Ltd v A&H Floors 2 Doors Australia Pty Ltd [2022] NSWSC 152
Andrew Hales | Karen Hanigan | Lauren Topper
Cosmo Cranes & Rigging Pty Ltd v EQ Constructions Pty Ltd [2022] NSWDC 6
Andrew Hales | Jessica Nesbit | Tony Issa
EQ Constructions Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1604 and
Iridium Developments Pty Ltd v A-Civil Aust Pty Ltd [2021] NSWSC 1601
Andrew Hales | Karen Hanigan | Alexander Mastrovangelis
Equa Building Services Pty Ltd v KLG Trading Pty Ltd [2021] NSWSC 1674
Andrew Hales | Maciej Getta | Cedric Barakat
The Estate of Sikos v TBPL1 Pty Ltd [2021] NSWSC 1523
Andrew Hales | Sophie Wallwork | Tom Lawler
Ventia Australia Pty Ltd v BSA Advanced Property Solutions (Fire) Pty Ltd [2021] NSWSC 1534
Andrew Hales | Tom Kearney | Isobel Carmody
V601 v Probuild [2021] VSC 849
Nikki Miller | Tom Kearney | Alice Tyson
Panel Concepts Pty Ltd v Tomkins Commercial & Industrial Builders Pty Ltd [2021] QDC 322
Sarah Ferrett | Sarah Cahill | Nikole Rabeling
HongKong Henson Industrial Limited v Victorian Ferries Pty Ltd [2021] FCA 1450
Andrew Orford | Petrina Macpherson | Gemma Galloway
Built Qld Pt Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd (No 2) [2021] QSC 301
Michael Creedon | Megan Sharkey | Oliver Waddingham
Meechan v Savco Earthmoving Pty Ltd [2021] QCA 264
Michael Creedon | Allie Flack | Oliver Waddingham
The Owners – Strata Plan No 87060 v Loulach Developments Pty Ltd (No 2) [2021] NSWSC 1068
Andrew Hales | Maciej Getta | Jenny Cohen
Crown Green Square Pty Ltd v Transport for NSW [2021] NSWSC 1557
Andrew Hales | Tom Kearney | Isobel Carmody
Santos Limited v Fluor Australia Pty Ltd & Anor [2021] QCA 204
Andrew Orford | Matt Hammond | Oliver Waddingham
Santos Limited v Fluor Australia Pty Ltd & Anor (No 3) [2021] QSC 281
Michael Creedon | Matt Hammond | Oliver Waddingham
Cairns Building and Construction Pty Ltd ATF P&T Kelly Trust t/as Phil Kelly Builders v Kaminaras & Anor [2021] QCAT 374
Michael Creedon | Clare Turner | Gemma Galloway
Cheshire Contractors Pty Ltd v Civil Mining & Construction [2021] QCA 212
Julie Whitehead | Allie Flack | Oliver Waddingham
Bothar Boring and Tunnelling (Australia) Pty Ltd v Ausipile Pty Ltd [2021] QCA 226
Sarah Ferrett | Matt Hammond | Gemma Galloway
Ventia Australia Pty Ltd v BSA Advanced Property Solutions (Fire) Pty Ltd [2021] NSWSC 1534
Andrew Hales | Tom Kearney | Isobel Carmody
Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd (No 2) [2021] QSC 231; Total Lifestyle Windows Pty Ltd v Aniko Constructions Pty Ltd (No 3) [2021] QSC 238
Sarah Ferrett | Hazal Gacka | Gemma Galloway
Day v Quince’s Quality Building Services Pty Ltd [2021] NSWCATAP 296
Andrew Hales | Claire Laverick | Tony Issa
Paolucci v Makedyn [2021] NSWCA 215
Andrew Hales | Nicholas Grewal | Jonin Ngo
Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QCA 223
Sarah Ferrett | Tom Kearney | Isobel Carmody
Russell Consolidated Pty Ltd v Russell Noble Constructions Pty Ltd [2021] WASC 155
Tom French | Candice Lamb | Ljubica Petrovic
North Queensland Pipeline No 1 Pty Ltd v QNI Resources Pty Ltd [2021] QSC 190
Julie Whitehead | Sarah Cahill | Tia Shadford
Tower Cranes International Pty Ltd v Boland Cranes Pty Ltd [2021] QDC 183
Michael Creedon, Alexandria Hammerton, Mikayla Colak
Sentinel Springwood Retail Pty Ltd & Ors v Tomlinson & Ors [2021] QDC 159
Michael Creedon, Luke Trimarchi, Daniel Szabo
Equinox Construction Pty Ltd v Henning & Anor [2021] QSC 223
Andrew Orford, Matt Hammond, Charlotte Lane
Enco Precast Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union & Ors [2021] ICQ 15
Samantha Betzien, Allie Flack, Daniel Szabo
CMC Property Pty Ltd & Ors v Rankin Investments (Qld) Pty Ltd & Anor [2021] QCA 173
Andrew Orford, Sam Rafter, Mikayla Colak
Jandson Pty Ltd v James [2021] NSWCATAP 274
Andrew Hales, Adriaan van der Merwe, Jack McFadden
Howell v Talevski [2021] NSWSC 1133
Andrew Hales, Laura-Rose Lynch, Tom Dearden
B & W Windows (Residential) Pty Ltd v Sibilia [2021] NSWCATAP 271
Andrew Hales, Maciej Getta, Jonathan Molina
Punton’s Shoes Pty Ltd v Citi-Con (Vic) Pty Ltd [2020] VSC 514
Peter Wood, Tom Kearney, Henry Chesterman
Goldwind Australia Pty Ltd v ALE Heavylift (Australia) Pty Ltd [2021] VSC 625
Nikki Miller, Tom Kearney, Alice Tyson
Bellini v Meldan (Vic) Pty Ltd (Building and Property) [2021] VCAT 833
Jeanette Barbaro, Tom Kearney, Michelle Yu
Rankin Investments (Qld) Pty Ltd & Anor v CMC Property Pty Ltd & Ors [2021] QCA 156
by Andrew Orford, Sam Rafter, Mikayla Colak
Queensland Building Services Authority v Samimi & another [2021] QDC 112
by David Pearce, James Knell, Tia Shadford
Schneider v Queensland Building and Construction Commission [2021] QCA 155
by David Pearce, Hazal Gacka and Charlotte Lane
Lendlease Engineering Pty Ltd v Owners Corporation No.1 & Ors [2021] VSC 338
by Jeanette Barbaro, Tom Kearney and Courtenay Wood
Building and Construction (Security of Payment) Act 2021 (WA)
by Sophie Wallwork
Design and Building Practitioners Regulation 2021 (NSW), Design and Building Practitioners Amendment (Miscellaneous) Regulation 2021 (NSW) and Building Legislation Amendment Act 2021 (NSW)
by Andrew Hales, William Vu
Valmont Interiors Pty Ltd v Giorgio Armani Australia Pty Ltd [2020] NSWCA 90
by Andrew Hales, Claire Laverick, Naomi Graham
Meechan v Savco Earth Moving Pty Ltd [2021] QDC 14
by Michael Creedon, Allie Flack, Isabella Impiazzi
Tesseract International Pty Ltd v Pascale Construction Pty Ltd [2021]SASCA 8
by James Kearney, Daina Marshall, Jack Eccleston
Growthbuilt Pty Ltd v Modern Touch Marble & Granite [2021] NSWSC 290
Andrew Hales, Michelle Knight, Will Ryan
Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QSC 39
by Sarah Ferrett, Matt Hammond, Tia Shadford